Location:

Port Adelaide, Port Augusta, Saint Agnes, and Mile End

Date:

2015 to 2026

Cost:

$20M – $200M

One team. One vision.
Total project certainty.

Project Brief

These purpose-built cement facilities are designed to support the efficient import, storage and distribution of bulk cement products within a high-demand industrial environment and this includes rural and portside environments. Developments incorporate large-scale storage infrastructure, conveying systems and heavy-duty operational areas to enable safe, continuous product handling and distribution. Engineered for durability, efficiency and long-term performance, they respond to the logistical and structural demands of bulk materials handling while supporting critical supply chain operations for the regions.

Key Considerations

  • Managing a complex staged approvals process through to Certificate of Occupancy and across multiple development phases (involving EPA and DIT)
  • Managing approvals and documentation to suit evolving operational requirements and support the progressive delivery of infrastructure and buildings
  • Coordinating approvals through to Certificate of Occupancy
  • Coordinating complex building services
  • Supporting innovative processes including production of green cement and heavily automated systems
  • Managing soil remediation works incorporating preloading of fill to achieve suitable ground performance
  • Site-wide stormwater design, including separation and control of clean and contaminated runoff, with appropriate collection, conveyance and discharge systems
  • Design of sediment and water quality basins with WSUD measures to treat runoff and meet environmental and regulatory requirements
  • Earthworks and grading design to manage site drainage, prevent cross-contamination and integrate with staging and operations

Further information: click here and here